ADDENDUM NO. 1
April 27, 2021
TO ALL VENDORS:
The following changes, additions, and/or deletions are hereby made a part of the contract documents for the above-referenced project, as fully and completely as if the same were fully set forth therein:
TECHNICAL SPECIFICATIONS
- Refer to part VAULT INSTALLATION. Replace section 8.4 with the following new section 8.4.
- The contractor shall extend the multi-duct outer sheath Three (3) inches inside of vault and provide an additional Eighteen to Twenty-Four (18 to 24) Inches of multi-duct “slack” beyond the inside wall of each vault.
All bidders shall acknowledge receipt and acceptance of ADDENDUM NO. 1 by submitting their bid documents on or before the applicable date of letting.